ProjectDataSet.TaskRow.TASK_TCPI Property
Task to complete performance index is the ratio of remaining available budget to remaining scheduled cost as of the status date.
Namespace: [Statusing Web service]
Service reference: http://ServerName:32843/[Project Service Application GUID]/PSI/Statusing.svc
Web service reference: http://ServerName/ProjectServerName/_vti_bin/PSI/Statusing.asmx?wsdl
Syntax
'Declaration
Public Property TASK_TCPI As Double
Get
Set
'Usage
Dim instance As ProjectDataSet.TaskRow
Dim value As Double
value = instance.TASK_TCPI
instance.TASK_TCPI = value
public double TASK_TCPI { get; set; }
Property Value
Type: System.Double
Remarks
Read-only.
TASK_TCPI = (TB_COST - TASK_BCWP) / (TB_COST - TASK_ACWP)