ProjectDataSet.TaskRow.TASK_FINISH_SLACK Property
The finish slack duration is the duration between the TASK_EARLY_FINISH date and the TASK_LATE_FINISH date.
Namespace: [Statusing Web service]
Service reference: http://ServerName:32843/[Project Service Application GUID]/PSI/Statusing.svc
Web service reference: http://ServerName/ProjectServerName/_vti_bin/PSI/Statusing.asmx?wsdl
Syntax
'Declaration
Public Property TASK_FINISH_SLACK As Integer
Get
Set
'Usage
Dim instance As ProjectDataSet.TaskRow
Dim value As Integer
value = instance.TASK_FINISH_SLACK
instance.TASK_FINISH_SLACK = value
public int TASK_FINISH_SLACK { get; set; }
Property Value
Type: System.Int32
Remarks
Read-only. The duration is indicated in tenths of minutes. For example, a value of 100 indicates 10 minutes.