ProjectDataSet.TaskRow.TB_FINISH Property

Task baseline finish is the planned completion date for the task at the time you saved a baseline.

Namespace:  [Project Web service]
Service reference: http://ServerName:32843/[Project Service Application GUID]/PSI/Project.svc
Web service reference: http://ServerName/ProjectServerName/_vti_bin/PSI/Project.asmx?wsdl

Syntax

'Declaration
Public Property TB_FINISH As DateTime
    Get
    Set
'Usage
Dim instance As ProjectDataSet.TaskRow
Dim value As DateTime

value = instance.TB_FINISH

instance.TB_FINISH = value
public DateTime TB_FINISH { get; set; }

Property Value

Type: System.DateTime

Remarks

Read-only.