ActualWork Element for Parent PeriodChange (SetAssignmentWorkData)
Applies to: Office 2010 | Project 2010 | Project Server 2010 | SharePoint Server 2010
In this article
Attributes
Child Elements
Parent Elements
Occurrences
Text Value
Specifies a timephased work data update to the Actual Work field and contains the new value for that field.
<ActualWork
Start="dateTime"
End="dateTime">
WorkValue
</TotalWork>
Attributes
Attribute |
Description |
---|---|
Start |
Required dateTime. The value for the beginning of the timephased period. |
End |
Required dateTime. The value for the end of the timephased period. |
Child Elements
None |
Parent Elements
Occurrences
Minimum: 0 Maximum: Unbounded |
Text Value
A text value is required. This text specifies the value that the Actual Work field is updated to.
You must represent work duration data in Project work time units (PWU). 1 PWU=1/1000 of a minute. 480,000 PWU=8 hours.
Example
The following example uses the ActualWork element to specify a timephased update of 40 hours over 5 days to the Actual Work field for the specified assignment.
<Changes>
<Proj ID="a47faeab-0f72-455a-b629-d62faf5fece6">
<Assn ID="352eb69a-a915-4849-b9f0-3d26d0d6e0a8">
<PeriodChange>
<ActualWork Start="2007-04-16T08:00:00" End="2007-04-20T16:00:00">19200000</ActualWork>
<OvertimeWork Start="2007-04-17T16:00:00" End="2007-04-17T18:00:00">480000</OvertimeWork>
<RemainingWork>920000</RemainingWork>
</PeriodChange>
</Assn>
</Proj>
</Changes>