Change Element
Applies to: Office 2010 | Project 2010 | Project Server 2010 | SharePoint Server 2010
In this article
Attributes
Child Elements
Parent Elements
Occurrences
Text Value
Specifies the field to change with a status update and contains the new value for that field.
<Change
PID="Integer"
ChangeNumber="Integer" >
UpdateValue
</Change>
Attributes
Attribute |
Description |
---|---|
PID |
Required Integer. Specifies the Project identifier (PID) of the field to change. |
ChangeNumber |
Optional Integer. Used to track changes. The value is -1 if changes are not tracked. ChangeNumber is not used if the parent is the Task element. |
Child Elements
None |
Parent Elements
Occurrences
Minimum: 0 in parent Assn, 1 in parent Task Maximum: Unbounded |
Text Value
A text value is required. This text specifies the update value for the field.
Note
The text value must match the data type required by the specified field.
Remarks
For information about updatable fields, PIDs, and required data types, see Supported Project Fields and Field Information for Statusing ChangeXML.
Example
The following example uses two Change elements to define two updates to a single task. The first Change element updates the Start field for the task to the value 8am January 10, 2007. The second Change element updates the Deadline field for the task to the value of 4pm January 31, 2007.
<Changes>
<Proj ID="a47faeab-0f72-455a-b629-d62faf5fece6">
<Task ID="0f8e477d-8dd9-4011-95cc-2499bb10cf10">
<Change PID="184549386">2007-01-10T08:00:00</Change>
<Change PID="184549394">2007-01-31T16:00:00</Change>
</Task>
</Proj>
</Changes>