ActualWork Element for Parent Change (SetAssignmentWorkData)
Applies to: Office 2010 | Project 2010 | Project Server 2010 | SharePoint Server 2010
In this article
Attributes
Child Elements
Parent Elements
Occurrences
Text Value
Specifies a work data update to the Actual Work field and contains the new value for that field.
<ActualWork>
WorkValue
</ActualWork>
Attributes
Attribute |
Description |
---|---|
None |
Child Elements
None |
Parent Elements
Occurrences
Minimum: 1 Maximum: 1 |
Text Value
A text value is required. This text specifies the value that the Actual Work field is updated to.
You must represent work duration data in Project work time units (PWU). 1 PWU=1/1000 of a minute. 480,000 PWU=8 hours.
Remarks
Note
If the value specified in the TotalWork element does not equal the sum of the values specified in the ActualWork and RemainingWork elements, a StatusingInvalidUpdateData error occurs.
Example
The following example uses the ActualWork element to update the Actual Work field to the value of 8 hours for the specified assignment.
<Changes>
<Proj ID="a47faeab-0f72-455a-b629-d62faf5fece6">
<Assn ID="6c9888a8-a782-47ac-a905-e84ad1fe0fb2">
<Change>
<ActualWork>480000</ActualWork>
<RemainingWork>960000</RemainingWork>
<TotalWork>1440000</TotalWork>
</Change>
</Assn>
</Proj>