ProjectDataSet.TaskRow.TASK_TCPI Property

Task to complete performance index is the ratio of remaining available budget to remaining scheduled cost as of the status date.

Namespace:  [Project Web service]
Service reference: http://ServerName:32843/[Project Service Application GUID]/PSI/Project.svc
Web service reference: http://ServerName/ProjectServerName/_vti_bin/PSI/Project.asmx?wsdl

Syntax

'Declaration
Public Property TASK_TCPI As Double
    Get
    Set
'Usage
Dim instance As ProjectDataSet.TaskRow
Dim value As Double

value = instance.TASK_TCPI

instance.TASK_TCPI = value
public double TASK_TCPI { get; set; }

Property Value

Type: System.Double

Remarks

Read-only.

TASK_TCPI = (TB_COST - TASK_BCWP) / (TB_COST - TASK_ACWP)

See Also

Reference

ProjectDataSet.TaskRow Class

ProjectDataSet.TaskRow Members

Project Web Service