PjSaveBaselineTo Enumeration
Contains constants that specify which fields to copy into.
Name |
Value |
Description |
---|---|---|
pjIntoBaseline |
0 |
All baseline information in the active project. |
pjIntoBaseline1 |
11 |
Baseline1 start and Baseline1 finish dates. |
pjIntoBaseline10 |
20 |
Baseline10 start and Baseline10 finish dates. |
pjIntoBaseline2 |
12 |
Baseline2 start and Baseline2 finish dates. |
pjIntoBaseline3 |
13 |
Baseline3 start and Baseline3 finish dates. |
pjIntoBaseline4 |
14 |
Baseline4 start and Baseline4 finish dates. |
pjIntoBaseline5 |
15 |
Baseline5 start and Baseline5 finish dates. |
pjIntoBaseline6 |
16 |
Baseline6 start and Baseline6 finish dates. |
pjIntoBaseline7 |
17 |
Baseline7 start and Baseline7 finish dates. |
pjIntoBaseline8 |
18 |
Baseline8 start and Baselin8 finish dates. |
pjIntoBaseline9 |
19 |
Baseline9 start and Baseline9 finish dates. |
pjIntoStart_Finish1 |
1 |
Dates in the Start1 and Finish1 custom fields. |
pjIntoStart_Finish10 |
10 |
Dates in the Start10 and Finish10 custom fields. |
pjIntoStart_Finish2 |
2 |
Dates in the Start2 and Finish2 custom fields. |
pjIntoStart_Finish3 |
3 |
Dates in the Start3 and Finish3 custom fields. |
pjIntoStart_Finish4 |
4 |
Dates in the Start4 and Finish4 custom fields. |
pjIntoStart_Finish5 |
5 |
Dates in the Start5 and Finish5 custom fields. |
pjIntoStart_Finish6 |
6 |
Dates in the Start6 and Finish6 custom fields. |
pjIntoStart_Finish7 |
7 |
Dates in the Start7 and Finish7 custom fields. |
pjIntoStart_Finish8 |
8 |
Dates in the Start8 and Finish8 custom fields. |
pjIntoStart_Finish9 |
9 |
Dates in the Start9 and Finish9 custom fields. |