PeriodChange Element
This content is outdated and is no longer being maintained. It is provided as a courtesy for individuals who are still using these technologies. This page may contain URLs that were valid when originally published, but now link to sites or pages that no longer exist.
Specifies the field to change with a timephased status update and contains the new value for that field.
<PeriodChange
PID = "Integer"
Start = "dateTime"
End = "dateTime">
UpdateValue
</PeriodChange>
Attributes
Attribute |
Description |
---|---|
PID |
Required Integer. Specifies the Project identifier (PID) of the field to change. |
Start |
Required dateTime. The value for the beginning of the timephased period. |
End |
Required dateTime. The value for the end of the timephased period. |
Child Elements
None |
Parent Elements
Occurrences
Minimum: 0 Maximum: Unbounded |
Text Value
A text value is required. This text specifies the value to update the field to.
Note |
---|
The text value must match the data type required by the specified field. |
Remarks
For information about updatable assignment fields, PIDs, and required data types, see Supported Project Fields and Field Information for Statusing ChangeXML.
Example
The following example specifies multiple timephased status updates for a single assignment. Three PeriodChange elements specify timephased updates to the Actual Work field. These updates use Project Time Unit values to add 4, 2, and 6 hours of actual work to the assignment with the timephasing specified by the Start and End attributes of the PeriodChange elements.
<Changes>
<Proj ID="a47faeab-0f72-455a-b629-d62faf5fece6">
<Assn ID="6c9888a8-a782-47ac-a905-e84ad1fe0fb2">
<PeriodChange PID="251658250" Start="2006-10-27T08:00:10" End="2006-10-27T12:00:10">240000</PeriodChange>
<PeriodChange PID="251658250" Start="2006-10-28T08:00:10" End="2006-10-28T12:00:10">120000</PeriodChange>
<PeriodChange PID="251658250" Start="2006-10-29T08:00:10" End="2006-10-29T14:00:10">360000</PeriodChange>
</Assn>
</Proj>
</Changes>