Compartir a través de


Default Dampener Period Field, Manufacturing Setup Table

Specifies a period of time during which you do not want the planning system to propose to reschedule existing supply orders forward. For more information, see Dampener Period.

This value in this field applies to all items except for items that have a different value in the Dampener Period field on the item card.

Additional Information

When a dampener time is set, an order is only rescheduled when the defined dampener time has passed since the order's original due date.

Note

The dampener time that is applied to an item can never be higher than the value in the item's Lot Accumulation Period field. This is because the inventory build-up time that occurs during a dampener period would conflict with the build-up period defined by the item's lot accumulation period. Accordingly, the default dampener period generally applies to all items. However, if an item's lot accumulation period is shorter than the default dampener period, then the item's dampener time equals its lot accumulation period.

Tip

For more information on how to work with fields and columns, see Work with Data. For assistance in finding specific pages, see Search.

Parent Tables

Table Location
Manufacturing Setup Table Manufacturing
Manufacturing Setup Table Manufacturing

See Also

Reference

Manufacturing Setup

Other Resources

Dampener Period
Time Bucket
Dampener Quantity
Lot Accumulation Period
Setup Best Practices: Global Planning Setup