Calculate capacity load on scheduled work orders
If you want to get an overview of the workload on resources for a specific period, you can use the Calculate capacity load page.
You can calculate capacity load based on:
- Maintenance workers
- Worker groups
- Tools
- Assets
To use the Calculate capacity load page, follow these steps:
- Go to Asset Management > Inquiries > Schedule > Capacity load. The Calculate capacity load dialog box displays where you can specify the parameters for the inquiry.
- In the Show field, you can select if you want to calculate. You can select Capacity, Reserved, or Remainder.
- If you set the Skip zero toggle to Yes, you won't see results containing zero.
- You can select the resources to calculate by setting the toggle for Worker, Maintenance worker group, Tool, or Asset to Yes.
- You can select the date and interval for the calculation. In the Interval type field, you can select Day, Week, Month, or Quarter.
- Specify the From date to run this calculation.
- In the Period frequency field, you can enter the number of intervals that you want to calculate. For example, if you select Week and enter 5 in the Period frequency field, you'll be calculating for five weeks from the start date.
- Select OK. An inquiry will display, like the following image.
- In the query, you can see the Load type, Reference number, Name, and hours for each day.