You're working on a project that has undefined requirements and new requirements are expected to occur during the project. What methodology would best suit this type of project?
Waterfall
Agile
Spiral
A new developer is joining the project team. You, as the project manager, must request a new environment for the developer to use. What kind of environment should you request?
A Tier 1 environment
A Tier 2 environment
A production environment