Approving and Modifying Change Requests
Updated: May 13, 2016
Applies To: System Center 2012 SP1 - Service Manager, System Center 2012 R2 Service Manager, System Center 2012 - Service Manager
The procedures in this section describe how to approve a change request in System Center 2012 – Service Manager.
For a detailed description of the complete scenario for approving a change request, see Sample Scenario: Managing Changes and Activities.
Complete the following steps to approve or modify a change request.
Task | Description |
---|---|
Step 1: How to Edit a Change Request | Describes how to edit a change request to add or revise details. |
Step 2: How to Add a Change Reviewer | Describes how to add a change reviewer to a change request. |
Step 3: How to Approve a Review Activity Using the Console | Describes how to approve a review activity for a change request. |
Step 4: How to Send Automated Activity and Change Request Notifications | Describes how to notify users when they have an activity that requires approval or when a change request is closed. |