ProjectDataSet.TaskRow.TASK_ACT_WORK property
Specifies the amount of work that has been done by the resources that are assigned to the task.
Namespace: WebSvcProject
Assembly: ProjectServerServices (in ProjectServerServices.dll)
Syntax
'Declaration
Public Property TASK_ACT_WORK As Double
Get
Set
'Usage
Dim instance As ProjectDataSet.TaskRow
Dim value As Double
value = instance.TASK_ACT_WORK
instance.TASK_ACT_WORK = value
public double TASK_ACT_WORK { get; set; }
Property value
Type: System.Double
Remarks
TASK_ACT_WORK is a calculated field.
Work is stored as thousandths of a minute. For example, a value of 10000 indicates 10 minutes.