Assignment Object Members
Project Developer Reference |
An Assignment object represents an assignment for a task or resource.
Methods
Name | Description | |
---|---|---|
![]() |
AppendNotes | Appends new text to the Notes field. |
![]() |
Delete | Deletes an object from its containing collection. |
![]() |
EnterpriseTeamMember | Returns whether the specified assignment belongs to the project. True if the assignment belongs to the specified project or False if the assignment does not belong to the specified project. |
![]() |
TimeScaleData | The description for this item will appear in the final release of Office 2007. |
Properties
Name | Description | |
---|---|---|
![]() |
ActualCost | Returns the actual cost for an assignment, resource, or task. Read-only Variant. |
![]() |
ActualFinish | Returns or sets the actual finish date of an assignment or task. Read-only for summary tasks. Read/write Variant. |
![]() |
ActualOvertimeCost | Returns the actual overtime cost for an assignment. Read/write Variant. |
![]() |
ActualOvertimeWork | Returns the actual overtime work (in minutes) for an assignment. Read/write Variant. |
![]() |
ActualOvtWorkProtected | Returns the actual overtime work (in minutes) for an Assignment object. Read/write Variant. |
![]() |
ActualStart | Returns or sets the actual start date of an assignment. Read/write Variant. |
![]() |
ActualWork | Returns or sets the actual work (in minutes) for an Assignment object. Read/write Variant. |
![]() |
ActualWorkProtected | Returns or sets the protected actual work (in minutes) for a Assignment object. Read/write Variant. |
![]() |
ACWP | Returns the ACWP for an Assignment. Read-only Variant. |
![]() |
Application | Returns an Application object. Read-only Object. |
![]() |
Baseline10BudgetCost | Returns or sets the baseline10 budget cost for an Assignment. Read/write Variant. |
![]() |
Baseline10BudgetWork | Returns or sets the baseline10 budget work (in hours) for an Assignment. Read/write Variant. |
![]() |
Baseline10Cost | Returns or sets the baseline cost for an Assignment. Read/write Variant. |
![]() |
Baseline10Finish | Returns or sets the baseline finish date of a task Assignment. Read/write Variant. |
![]() |
Baseline10Start | Returns or sets the baseline start date of a task Assignment. Read/write Variant. |
![]() |
Baseline10Work | Returns or sets the baseline work (in minutes) for an Assignment. Read/write Variant. |
![]() |
Baseline1BudgetCost | Returns or sets the baseline1 budget cost for an Assignment. Read/write Variant. |
![]() |
Baseline1BudgetWork | Returns or sets the baseline1 budget work (in hours) for an Assignment. Read/write Variant. |
![]() |
Baseline1Cost | Returns or sets the baseline cost for an Assignment. Read/write Variant. |
![]() |
Baseline1Finish | Returns or sets the baseline finish date of a task Assignment. Read/write Variant. |
![]() |
Baseline1Start | Returns or sets the baseline start date of a task Assignment. Read/write Variant. |
![]() |
Baseline1Work | Returns or sets the baseline work (in minutes) for an Assignment. Read/write Variant. |
![]() |
Baseline2BudgetCost | Returns or sets the baseline2 budget cost for an Assignment. Read/write Variant. |
![]() |
Baseline2BudgetWork | Returns or sets the baseline2 budget work (in hours) for an Assignment. Read/write Variant. |
![]() |
Baseline2Cost | Returns or sets the baseline cost for an Assignment. Read/write Variant. |
![]() |
Baseline2Finish | Returns or sets the baseline finish date of a task Assignment. Read/write Variant. |
![]() |
Baseline2Start | Returns or sets the baseline start date of a task Assignment. Read/write Variant.Read/write |
![]() |
Baseline2Work | Returns or sets the baseline work (in minutes) for an Assignment. Read/write Variant. |
![]() |
Baseline3BudgetCost | Returns or sets the baseline3 budget cost for an Assignment. Read/write Variant. |
![]() |
Baseline3BudgetWork | Returns or sets the baseline3 budget work (in hours) for an Assignment. Read/write Variant. |
![]() |
Baseline3Cost | Returns or sets the baseline cost for an Assignment. Read/write Variant. |
![]() |
Baseline3Finish | Returns or sets the baseline finish date of a task Assignment. Read/write Variant. |
![]() |
Baseline3Start | Returns or sets the baseline start date of a task Assignment. Read/write Variant.Read/write |
![]() |
Baseline3Work | Returns or sets the baseline work (in minutes) for an Assignment. Read/write Variant. |
![]() |
Baseline4BudgetCost | Returns or sets the baseline4 budget cost for an Assignment. Read/write Variant. |
![]() |
Baseline4BudgetWork | Returns or sets the baseline4 budget work (in hours) for an Assignment. Read/write Variant. |
![]() |
Baseline4Cost | Returns or sets the baseline cost for an Assignment. Read/write Variant. |
![]() |
Baseline4Finish | Returns or sets the baseline finish date of a task Assignment. Read/write Variant. |
![]() |
Baseline4Start | Returns or sets the baseline start date of a task Assignment. Read/write Variant. |
![]() |
Baseline4Work | Returns or sets the baseline work (in minutes) for an Assignment. Read/write Variant. |
![]() |
Baseline5BudgetCost | Returns or sets the baseline5 budget cost for an Assignment. Read/write Variant. |
![]() |
Baseline5BudgetWork | Returns or sets the baseline5 budget work (in hours) for an Assignment. Read/write Variant. |
![]() |
Baseline5Cost | Returns or sets the baseline cost for an Assignment. Read/write Variant. |
![]() |
Baseline5Finish | Returns or sets the baseline finish date of a task Assignment . Read/write Variant. |
![]() |
Baseline5Start | Returns or sets the baseline start date of a task Assignment. Read/write Variant. |
![]() |
Baseline5Work | Returns or sets the baseline work (in minutes) for an Assignment. Read/write Variant. |
![]() |
Baseline6BudgetCost | Returns or sets the baseline6 budget cost for an Assignment. Read/write Variant. |
![]() |
Baseline6BudgetWork | Returns or sets the baseline6 budget work (in hours) for an Assignment. Read/write Variant. |
![]() |
Baseline6Cost | Returns or sets the baseline cost for an Assignment. Read/write Variant. |
![]() |
Baseline6Finish | Returns or sets the baseline finish date of a task Assignment. Read/write Variant. |
![]() |
Baseline6Start | Returns or sets the baseline start date of a task Assignment. Read/write Variant. |
![]() |
Baseline6Work | Returns or sets the baseline work (in minutes) for an Assignment. Read/write Variant. |
![]() |
Baseline7BudgetCost | Returns or sets the baseline7 budget cost for an Assignment. Read/write Variant. |
![]() |
Baseline7BudgetWork | Returns or sets the baseline7 budget work (in hours) for an Assignment. Read/write Variant. |
![]() |
Baseline7Cost | Returns or sets the baseline cost for an Assignment. Read/write Variant. |
![]() |
Baseline7Finish | Returns or sets the baseline finish date of a task Assignment. Read/write Variant. |
![]() |
Baseline7Start | Returns or sets the baseline start date of a task Assignment. Read/write Variant. |
![]() |
Baseline7Work | Returns or sets the baseline work (in minutes) for an Assignment. Read/write Variant. |
![]() |
Baseline8BudgetCost | Returns or sets the baseline8 budget cost for an Assignment. Read/write Variant. |
![]() |
Baseline8BudgetWork | Returns or sets the baseline8 budget work (in hours) for an Assignment. Read/write Variant. |
![]() |
Baseline8Cost | Returns or sets the baseline cost for an Assignment. Read/write Variant. |
![]() |
Baseline8Finish | Returns or sets the baseline finish date of a task Assignment. Read/write Variant. |
![]() |
Baseline8Start | Returns or sets the baseline start date of a task Assignment. Read/write Variant. |
![]() |
Baseline8Work | Returns or sets the baseline work (in minutes) for an Assignment. Read/write Variant. |
![]() |
Baseline9BudgetCost | Returns or sets the baseline9 budget cost for an Assignment. Read/write Variant. |
![]() |
Baseline9BudgetWork | Returns or sets the baseline9 budget work (in hours) for an Assignment. Read/write Variant. |
![]() |
Baseline9Cost | Returns or sets the baseline cost for an Assignment. Read/write Variant. |
![]() |
Baseline9Finish | Returns or sets the baseline finish date of a task Assignment. Read/write Variant. |
![]() |
Baseline9Start | Returns or sets the baseline start date of a task Assignment. Read/write Variant. |
![]() |
Baseline9Work | Returns or sets the baseline work (in minutes) for an Assignment. Read/write Variant. |
![]() |
BaselineBudgetCost | Returns or sets the baseline budget cost for an Assignment. Read/write Variant. |
![]() |
BaselineBudgetWork | Returns or sets the baseline budget work (in hours) for an Assignment. Read/write Variant. |
![]() |
BaselineCost | Returns or sets the baseline cost for an Assignment. Read/write Variant. |
![]() |
BaselineFinish | Returns or sets the baseline finish date of a task Assignment. Read/write Variant. |
![]() |
BaselineStart | Returns or sets the baseline start date of a task Assignment. Read/write Variant. |
![]() |
BaselineWork | Returns or sets the baseline work (in minutes) for an Assignment. Read/write Variant. |
![]() |
BCWP | Returns the BCWP for an Assignment. Read-only Variant. |
![]() |
BCWS | Returns the BCWS for an Assignment. Read-only Variant. |
![]() |
BookingType | Returns the booking type for an assignment. Can be one of the following PjBookingTypes constants: pjBookingTypeCommitted or pjBookingTypeProposed. Read/write Long. |
![]() |
BudgetCost | Returns or sets the budget cost for an Assignment. Read/write Variant. |
![]() |
BudgetWork | Returns or sets the budget work (in hours) for an Assignment. Read/write Variant. |
![]() |
Confirmed | Returns the results of task assignments in a 1st_Project12 mail message. True if a resource of a project or task has accepted the assignment. Read/write Boolean. |
![]() |
Cost | Returns the cost of an Assignment. Read/write Variant. |
![]() |
Cost1 | Returns the cost of an Assignment. Read/write Variant. |
![]() |
Cost10 | Returns the cost of an Assignment. Read/write Variant. |
![]() |
Cost2 | Returns the cost of an Assignment. Read/write Variant. |
![]() |
Cost3 | Returns the cost of an Assignment. Read/write Variant. |
![]() |
Cost4 | Returns the cost of an Assignment. Read/write Variant. |
![]() |
Cost5 | Returns the cost of an Assignment. Read/write Variant. |
![]() |
Cost6 | Returns the cost of an Assignment. Read/write Variant. |
![]() |
Cost7 | Returns the cost of an Assignment. Read/write Variant. |
![]() |
Cost8 | Returns the cost of an Assignment. Read/write Variant. |
![]() |
Cost9 | Returns the cost of an Assignment. Read/write Variant. |
![]() |
CostRateTable | Returns or sets the cost rate table in effect for the assignment. Read/write Variant. |
![]() |
CostVariance | Returns the variance between the baseline cost and the cost of an Assignment. Read-only Variant. |
![]() |
Created | Returns the date an Assignment was created. Read-only Variant. |
![]() |
CV | Returns the cost variance for an Assignment. Read-only Variant. |
![]() |
Date1 | Returns or sets the value in an additional date field for an Assignment. Read/write Variant. |
![]() |
Date10 | Returns or sets the value in an additional date field for an Assignment. Read/write Variant. |
![]() |
Date2 | Returns or sets the value in an additional date field for an Assignment. Read/write Variant. |
![]() |
Date3 | Returns or sets the value in an additional date field for an Assignment. Read/write Variant. |
![]() |
Date4 | Returns or sets the value in an additional date field for an Assignment. Read/write Variant. |
![]() |
Date5 | Returns or sets the value in an additional date field for an Assignment. Read/write Variant. |
![]() |
Date6 | Returns or sets the value in an additional date field for an Assignment. Read/write Variant. |
![]() |
Date7 | Returns or sets the value in an additional date field for an Assignment. Read/write Variant. |
![]() |
Date8 | Returns or sets the value in an additional date field for an Assignment. Read/write Variant. |
![]() |
Date9 | Returns or sets the value in an additional date field for an Assignment. Read/write Variant. |
![]() |
Delay | Returns or sets the amount of time an assignment is delayed in minutes. Read/write Variant. |
![]() |
Duration1 | Returns or sets the value of an additional duration field for an Assignment. Read/writeVariant. |
![]() |
Duration10 | Returns or sets the value of an additional duration field for an Assignment. Read/writeVariant. |
![]() |
Duration2 | Returns or sets the value of an additional duration field for an Assignment. Read/writeVariant. |
![]() |
Duration3 | Returns or sets the value of an additional duration field for an Assignment. Read/write Variant. |
![]() |
Duration4 | Returns or sets the value of an additional duration field for an Assignment. Read/write Variant. |
![]() |
Duration5 | Returns or sets the value of an additional duration field for an Assignment. Read/write Variant. |
![]() |
Duration6 | Returns or sets the value of an additional duration field for an Assignment. Read/write Variant. |
![]() |
Duration7 | Returns or sets the value of an additional duration field for an Assignment. Read/write Variant. |
![]() |
Duration8 | Returns or sets the value of an additional duration field for an Assignment. Read/write Variant. |
![]() |
Duration9 | Returns or sets the value of an additional duration field for an Assignment. Read/write Variant. |
![]() |
Finish | Returns or sets the finish date of an assignment. Read/write Variant. |
![]() |
Finish1 | Returns or sets an additional finish date of an assignment. Read/write Variant. |
![]() |
Finish10 | Returns or sets an additional finish date of an assignment. Read/write Variant. |
![]() |
Finish2 | Returns or sets an additional finish date of an assignment. Read/write Variant. |
![]() |
Finish3 | Returns or sets an additional finish date of an assignment. Read/write Variant. |
![]() |
Finish4 | Returns or sets an additional finish date of an assignment. Read/write Variant. |
![]() |
Finish5 | Returns or sets an additional finish date of an assignment. Read/write Variant. |
![]() |
Finish6 | Returns or sets an additional finish date of an assignment. Read/write Variant. |
![]() |
Finish7 | Returns or sets an additional finish date of an assignment. Read/write Variant. |
![]() |
Finish8 | Returns or sets an additional finish date of an assignment. Read/write Variant. |
![]() |
Finish9 | Returns or sets an additional finish date of an assignment. Read/write Variant. |
![]() |
FinishVariance | Returns the variance (in minutes) between the baseline finish date and the finish date of an Assignment. Read-only Variant |
![]() |
FixedMaterialAssignment | True if the consumption of the assigned material resource occurs in a single, fixed amount. False if the consumption occurs at an hourly rate. Read-only Boolean. |
![]() |
Flag1 | True if the flag associated with an Assignment is set. Read/write Boolean. |
![]() |
Flag10 | True if the flag associated with an Assignment is set. Read/write Boolean. |
![]() |
Flag11 | True if the flag associated with an Assignment is set. Read/write Boolean. |
![]() |
Flag12 | True if the flag associated with an Assignment is set. Read/write Boolean. |
![]() |
Flag13 | True if the flag associated with an Assignment is set. Read/write Boolean. |
![]() |
Flag14 | True if the flag associated with an Assignment is set. Read/write Boolean. |
![]() |
Flag15 | True if the flag associated with an Assignment is set. Read/write Boolean. |
![]() |
Flag16 | True if the flag associated with an Assignment is set. Read/write Boolean. |
![]() |
Flag17 | True if the flag associated with an Assignment is set. Read/write Boolean. |
![]() |
Flag18 | True if the flag associated with an Assignment is set. Read/write Boolean. |
![]() |
Flag19 | True if the flag associated with an Assignment is set. Read/write Boolean. |
![]() |
Flag2 | True if the flag associated with an Assignment is set. Read/write Boolean. |
![]() |
Flag20 | True if the flag associated with an Assignment is set. Read/write Boolean. |
![]() |
Flag3 | True if the flag associated with an Assignment is set. Read/write Boolean. |
![]() |
Flag4 | True if the flag associated with an Assignment is set. Read/write Boolean. |
![]() |
Flag5 | True if the flag associated with an Assignment is set. Read/write Boolean. |
![]() |
Flag6 | True if the flag associated with an Assignment is set. Read/write Boolean. |
![]() |
Flag7 | True if the flag associated with an Assignment is set. Read/write Boolean. |
![]() |
Flag8 | True if the flag associated with an Assignment is set. Read/write Boolean. |
![]() |
Flag9 | True if the flag associated with an Assignment is set. Read/write Boolean. |
![]() |
Guid | Returns the class identifier of the object. Read-only. |
![]() |
Hyperlink | Returns or sets a friendly name representing a hyperlink address. The name may also be a URL or UNC path. Read/write String. |
![]() |
HyperlinkAddress | Returns or sets the URL or UNC path of a document. Read/write String. |
![]() |
HyperlinkHREF | Returns or sets a combination of the hyperlink address and subaddress, separated by a "#". Read/write String. |
![]() |
HyperlinkScreenTip | Returns or sets a ScreenTip for the hyperlink. Read/write String. |
![]() |
HyperlinkSubAddress | Returns or sets the address of a location within the target document. Read/write String. |
![]() |
Index | Returns the index of an object in its containing collection. Read-only Long. |
![]() |
LevelingDelay | Returns or sets the amount to delay the Assignment due to leveling. Read/write Variant. |
![]() |
LinkedFields | True if the Assignment contains fields that are linked to other applications through OLE. Read-only Boolean. |
![]() |
Notes | Returns or sets the notes for an assignment. Read/write String. |
![]() |
Number1 | Returns or sets a number associated with an Assignment. Read/write Double. |
![]() |
Number10 | Returns or sets a number associated with an Assignment. Read/write Double. |
![]() |
Number11 | Returns or sets a number associated with an Assignment. Read/write Double. |
![]() |
Number12 | Returns or sets a number associated with an Assignment. Read/write Double. |
![]() |
Number13 | Returns or sets a number associated with an Assignment. Read/write Double. |
![]() |
Number14 | Returns or sets a number associated with an Assignment. Read/write Double. |
![]() |
Number15 | Returns or sets a number associated with an Assignment. Read/write Double. |
![]() |
Number16 | Returns or sets a number associated with an Assignment. Read/write Double. |
![]() |
Number17 | Returns or sets a number associated with an Assignment. Read/write Double. |
![]() |
Number18 | Returns or sets a number associated with an Assignment. Read/write Double. |
![]() |
Number19 | Returns or sets a number associated with an Assignment. Read/write Double. |
![]() |
Number2 | Returns or sets a number associated with an Assignment. Read/write Double. |
![]() |
Number20 | Returns or sets a number associated with an Assignment. Read/write Double. |
![]() |
Number3 | Returns or sets a number associated with an Assignment. Read/write Double. |
![]() |
Number4 | Returns or sets a number associated with an Assignment. Read/write Double. |
![]() |
Number5 | Returns or sets a number associated with an Assignment. Read/write Double. |
![]() |
Number6 | Returns or sets a number associated with an Assignment. Read/write Double. |
![]() |
Number7 | Returns or sets a number associated with an Assignment. Read/write Double. |
![]() |
Number8 | Returns or sets a number associated with an Assignment. Read/write Double. |
![]() |
Number9 | Returns or sets a number associated with an Assignment. Read/write Double. |
![]() |
Overallocated | True if an assignment is overallocated. Read-only Boolean. |
![]() |
OvertimeCost | Returns the overtime cost for an Assignment. Read-only Variant. |
![]() |
OvertimeWork | Returns or sets the overtime work. Read/write Variant. |
![]() |
Owner | Sets or gets the name of the assignment owner. Read/write String. |
![]() |
Parent | Returns the parent of the object. Read-only Object. |
![]() |
Peak | Returns the largest number of resource units assigned for the assignment. Read-only Variant. |
![]() |
PercentWorkComplete | Returns or sets the percentage of work complete for an Assignment. Read/write Variant. |
![]() |
Project | Returns the name of the project containing the Assignment. Read-only String. |
![]() |
RegularWork | Returns the amount of regular work for an Assignment. Read/write Variant. |
![]() |
RemainingCost | Returns the remaining cost for an Assignment. Read-only Variant. |
![]() |
RemainingOvertimeCost | Returns the remaining overtime cost for an Assignment. Read-only Variant. |
![]() |
RemainingOvertimeWork | Returns the remaining overtime work (in minutes) for an Assignment. Read/write Variant. |
![]() |
RemainingWork | Returns or sets the remaining work (in minutes) for an Assignment. Read/write Variant. |
![]() |
ResourceGuid | Returns or sets the class identifier of the resource. Read/write. |
![]() |
ResourceID | Returns or sets the identification number of a resource in an assignment. Read/write Long. |
![]() |
ResourceName | Returns or sets the name of the resource in an assignment. Read/write String. |
![]() |
ResourceRequestType | Returns or sets the type of resource request for the assignment. Can be one of the following PjResourceRequestType constants: pjResourceRequestTypeDemand, pjResourceRequestTypeNone, or pjResourceRequestTypeRequest. Read/write Long. |
![]() |
ResourceType | Returns the type of an assignment's resource. Can be one of the following PjResourceTypes constants: pjResourceTypeWork or pjResourceTypeMaterial. Read-only Long. |
![]() |
ResourceUniqueID | Returns or sets a unique identification number of a resource in an assignment. Read/write Long. |
![]() |
ResponsePending | True if a response has not been received for a TeamAssign message. Read/write Boolean. |
![]() |
Start | Returns or sets the start date of an Assignment. Read/write Variant. |
![]() |
Start1 | Returns or sets an additional start date for an Assignment. Read/write Variant. |
![]() |
Start10 | Returns or sets an additional start date for an Assignment. Read/write Variant. |
![]() |
Start2 | Returns or sets an additional start date for an Assignment. Read/write Variant. |
![]() |
Start3 | Returns or sets an additional start date for an Assignment. Read/write Variant. |
![]() |
Start4 | Returns or sets an additional start date for an Assignment. Read/write Variant. |
![]() |
Start5 | Returns or sets an additional start date for an Assignment. Read/write Variant. |
![]() |
Start6 | Returns or sets an additional start date for an Assignment. Read/write Variant. |
![]() |
Start7 | Returns or sets an additional start date for an Assignment. Read/write Variant. |
![]() |
Start8 | Returns or sets an additional start date for an Assignment. Read/write Variant. |
![]() |
Start9 | Returns or sets an additional start date for an Assignment. Read/write Variant. |
![]() |
StartVariance | Returns the variance (in minutes) between the baseline start date and the start date of an assignment or task. Read-only Variant. |
![]() |
Summary | True if the assignment is to a summary task. Read-only Boolean. |
![]() |
SV | Returns the SV of an Assignment. Read-only Variant. |
![]() |
TaskGuid | Returns or sets the class identifier of the task. Read/write. |
![]() |
TaskID | Returns or sets the identification number of a task in an assignment. Read/write Long. |
![]() |
TaskName | Returns or sets the name of a task in an assignment. Read/write String. |
![]() |
TaskOutlineNumber | Returns the task outline number of a specified assignment. Read-only String. |
![]() |
TaskSummaryName | Returns or sets a unique identification number of a resource in an assignment. Read/write Long. |
![]() |
TaskUniqueID | Returns or sets a unique identification number of a task in an assignment. Read/write Long. |
![]() |
TeamStatusPending | True if a response has not been received for a progress request message. Read/write Boolean. |
![]() |
Text1 | Returns or sets text associated with an Assignment. Read/write String. |
![]() |
Text10 | Returns or sets text associated with an Assignment. Read/write String. |
![]() |
Text11 | Returns or sets text associated with an Assignment. Read/write String. |
![]() |
Text12 | Returns or sets text associated with an Assignment. Read/write String. |
![]() |
Text13 | Returns or sets text associated with an Assignment. Read/write String. |
![]() |
Text14 | Returns or sets text associated with an Assignment. Read/write String. |
![]() |
Text15 | Returns or sets text associated with an Assignment. Read/write String. |
![]() |
Text16 | Returns or sets text associated with an Assignment. Read/write String. |
![]() |
Text17 | Returns or sets text associated with an Assignment. Read/write String. |
![]() |
Text18 | Returns or sets text associated with an Assignment. Read/write String. |
![]() |
Text19 | Returns or sets text associated with an Assignment. Read/write String. |
![]() |
Text2 | Returns or sets text associated with an Assignment. Read/write String. |
![]() |
Text20 | Returns or sets text associated with an Assignment. Read/write String. |
![]() |
Text21 | Returns or sets text associated with an Assignment. Read/write String. |
![]() |
Text22 | Returns or sets text associated with an Assignment. Read/write String. |
![]() |
Text23 | Returns or sets text associated with an Assignment. Read/write String. |
![]() |
Text24 | Returns or sets text associated with an Assignment. Read/write String. |
![]() |
Text25 | Returns or sets text associated with an Assignment. Read/write String. |
![]() |
Text26 | Returns or sets text associated with an Assignment. Read/write String. |
![]() |
Text27 | Returns or sets text associated with an Assignment. Read/write String. |
![]() |
Text28 | Returns or sets text associated with an Assignment. Read/write String. |
![]() |
Text29 | Returns or sets text associated with an Assignment. Read/write String. |
![]() |
Text3 | Returns or sets text associated with an Assignment. Read/write String. |
![]() |
Text30 | Returns or sets text associated with an Assignment. Read/write String. |
![]() |
Text4 | Returns or sets text associated with an Assignment. Read/write String. |
![]() |
Text5 | Returns or sets text associated with an Assignment. Read/write String. |
![]() |
Text6 | Returns or sets text associated with an Assignment. Read/write String. |
![]() |
Text7 | Returns or sets text associated with an Assignment. Read/write String. |
![]() |
Text8 | Returns or sets text associated with an Assignment. Read/write String. |
![]() |
Text9 | Returns or sets text associated with an Assignment. Read/write String. |
![]() |
UniqueID | Returns the unique identification number of an Assignment. Read-only Long. |
![]() |
Units | Returns or sets the number of resource units. Read-write Variant. |
![]() |
UpdateNeeded | True if the resource assigned to a task needs to be updated regarding the status of the task. Read-only Boolean. |
![]() |
VAC | Returns the VAC for an Assignment. Read-only Variant. |
![]() |
WBS | Returns or sets the WBS code of a task. Read/write String. |
![]() |
Work | Returns or sets the work (in minutes) for an Assignment. Read/write Variant. |
![]() |
WorkContour | Returns or sets the type of work contour for a resource assignment. Can be one of the following PjWorkContourType constants: pjBackLoaded, pjBell, pjContour, pjDoublePeak, pjEarlyPeak, pjFlat, pjFrontLoaded, pjLatePeak, or pjTurtle. The default value is pjFlat. Read/write Long. |
![]() |
WorkVariance | Returns the variance between the baseline work and the work for an Assignment. Read-only Variant. |