Share via


How to: Calculate Production Order Routing Lines

If you have amended production order lines, you must also refresh the routing of the production order.

In the following procedure, the routing lines are calculated for a firm planned production order. This can also be done for production orders with a different status.

To calculate production order routing lines

  1. In the Search box, enter Firm Planned Prod. Order, and then choose the related link.

  2. Open the relevant firm planned production order from the list.

  3. On the Actions tab, in the Functions group, choose Refresh. The Refresh Production Order window opens.

  4. On the Production Order FastTab, the current production order has been selected as a default.

  5. The following table describes the options available for this batch job.

    Option Selection Description

    Scheduling Direction

    Forward

    This field has no effect on the outcome.

    Backward

    This field has no effect on the outcome.

    Calculate

    Lines

    You must leave the field blank to retain the current production order line.

    Routings

    Select this field to calculate routings.

    Component Need

    This field has no effect on the outcome.

    Warehouse

    Create Inbound Request

    This field has no effect on the outcome.

  6. Choose the OK button to confirm your selections. The production order routing lines are refreshed.

Note

Calculating production order routing lines deletes previous changes in the routings.

See Also

Tasks

How to: Refresh Production Orders
How to: Calculate Production Order Components
How to: Calculate Lines from Production Order Headers