ReqCalc.createProcessTasks Method [AX 2012]
Creates the tasks for the complete master planning process.
Syntax
protected void createProcessTasks()
Run On
Called
Remarks
The tasks are as follows:
Pre-Update
Update Item List- these tasks are created by the Pre-Update task
Post-Update
Pre-Coverage
Coverage, Init Level - one task for each level
Coverage, Item List - one task for each item list
Coverage, Partitioning resources - one task for each level
Coverage, Schedule resources - one task for each order bundle
Coverage, Finalize Level - one task for each level
Pre-Futures
Futures, Receipts - one task for each item list
Futures, Partitioning resources - one task for each level
Futures, Schedule resources - one task for each order bundle
Futures, Issues - one task for each item list
Pre-Actions
Actions - one task for each item list
Auto-Coverage
Update item level
Update dynamic plan