TotalSlack Element
The amount of time a task can be delayed without delaying a project's finish date. Time is in tenths of a minute.
<TotalSlack>
IntegerValue
</TotalSlack>
Parent Elements
Occurrences
Minimum: 0 Maximum: 1 |
Example
The following example shows a task can be delayed by two days, if the work day is eight hours (2 days x 8 hours/day x 60 minutes/hour x 10 tenths/minute = 9600 tenths). The actual slack time available in this case is the same as the total slack.
<Task>
. . .
<FreeSlack>9600</FreeSlack>
<TotalSlack>9600</TotalSlack>
. . .
</Task>