RemainingDuration Element
The amount of time required to complete the unfinished portion of a task.
<RemainingDuration>
DurationValue
</RemainingDuration>
Parent Elements
Occurrences
Minimum: 0 Maximum: 1 |
Remarks
Remaining duration can be calculated in two ways, either based on percent complete or on actual duration.