OverAllocated Element
For a Task, Overallocated indicates whether an assigned resource on a task has been assigned to more work on the task than can be done within the normal working capacity.
For a Resource, it indicates whether the resource is assigned more work on all tasks than can be done within the normal working capacity.
For an Assignment, it indicates whether a resource is assigned to more work on a specific task than can be done within the resource's normal working capacity.
<Overallocated>
BooleanValue
</Overallocated>
Parent Elements
Occurrences
Minimum: 0 Maximum: 1 |
Text Value
A text value of type boolean is required.
Value |
Description |
---|---|
0 |
False |
1 |
True |
See Also
Concepts
Task Elements and XML Structure
XML Schema for the Tasks Element
Resource Elements and XML Structure
XML Schema for the Resources Element