Yes, you could combine these two formulas in one.
In the Expected Approval calculated column,
=IF([Submission Type]="Initial";IF(AND([RFI-V]="Yes";[RFI-A]="Yes";[Winter Clock Stop]="Yes");[Submission date]+128;IF(AND([RFI-V]="No";[RFI-A]="No";[Winter Clock Stop]="Yes");[Submission date]+42;IF(AND([RFI-V]="Yes";[RFI-A]="No";[Winter Clock Stop]="Yes");[Submission date]+60;IF(AND([RFI-V]="No";[RFI-A]="Yes";[Winter Clock Stop]="Yes");[Submission date]+80;IF(AND([RFI-V]="Yes";[RFI-A]="Yes";[Winter Clock Stop]="No");[Submission date]+111;IF(AND([RFI-V]="No";[RFI-A]="No";[Winter Clock Stop]="No");[Submission date]+25;IF(AND([RFI-V]="Yes";[RFI-A]="No";[Winter Clock Stop]="No");[Submission date]+43;IF(AND([RFI-V]="No";[RFI-A]="Yes";[Winter Clock Stop]="No");[Submission date]+63;""))))))));IF(AND([RFI-V]="Yes";[RFI-A]="Yes";[Winter Clock Stop]="Yes");[Submission date]+109;IF(AND([RFI-V]="No";[RFI-A]="No";[Winter Clock Stop]="Yes");[Submission date]+74;IF(AND([RFI-V]="Yes";[RFI-A]="No";[Winter Clock Stop]="Yes");[Submission date]+90;IF(AND([RFI-V]="No";[RFI-A]="Yes";[Winter Clock Stop]="Yes");[Submission date]+93;IF(AND([RFI-V]="Yes";[RFI-A]="Yes";[Winter Clock Stop]="No");[Submission date]+92;IF(AND([RFI-V]="No";[RFI-A]="No";[Winter Clock Stop]="No");[Submission date]+57;IF(AND([RFI-V]="Yes";[RFI-A]="No";[Winter Clock Stop]="No");[Submission date]+73;IF(AND([RFI-V]="No";[RFI-A]="Yes";[Winter Clock Stop]="No");[Submission date]+76;"")))))))))
In the Days calculated column,
=IF([Expected Approval]<[Actual Approval Date];DATEDIF([Expected Approval];[Actual Approval Date];"d")-INT(DATEDIF([Expected Approval];[Actual Approval Date];"d")/7)*2-IF(WEEKDAY([Actual Approval Date])<WEEKDAY([Expected Approval]);2;IF(OR(WEEKDAY([Actual Approval Date])=7;WEEKDAY([Expected Approval])=1);1;0));IF([Expected Approval]>[Actual Approval Date];-(DATEDIF([Actual Approval Date];[Expected Approval];"d")-INT(DATEDIF([Actual Approval Date];[Expected Approval];"d")/7)*2-IF(WEEKDAY([Expected Approval])<WEEKDAY([Actual Approval Date]);2;IF(OR(WEEKDAY([Expected Approval])=7;WEEKDAY([Actual Approval Date])=1);1;0)))))
Result:
If the answer is helpful, please click "Accept Answer" and kindly upvote it. If you have extra questions about this answer, please click "Comment".
Note: Please follow the steps in our documentation to enable e-mail notifications if you want to receive the related email notification for this thread.