ITIL Adoption using PMO and Project Management Best Practice

Abstract

The following paper explores the concept of using project management methods and practices to

increase the opportunities for success with ITIL adoption efforts. It also describes several high-level

approaches for consideration using the Project Management Office (PMO) best practice that is

described in the Project Management Body of Knowledge (PMBOK). For many organizations, ITIL

adoption is a tremendous undertaking that requires a significant investment of time and resources to be

successful. The PMO model is best positioned to manage the diverse concerns of ITIL adoption, to

ensure stakeholder needs are met, and that the different components of the effort are coordinated and

synchronized.

I. The Challenge of Bringing ITIL to Life (From Theory to Reality)

Since its inception in the 1980’s, the ITIL framework has grown to become one of the leading

frameworks for managing IT Service Delivery. Over time, the good practices and methods offered as

part of the framework have proven to be the most effective in helping organizations close the gap

between the business and IT. Much of its success and appeal can be attributed to ITIL’s common sense

approach to working through many universal issues experienced by a diverse group of commercial and

government organizations. Evidence of ITIL’s success and appeal can be seen in a recent Gartner study

stating that ‘according to global trends, 90% of organizations are expected to have moved toward ITIL

(V3), in terms of active ITIL implementation efforts, by 2012’ (5). Further confirmation of

the rising acceptance trend can be seen in recent study conducted by Computer Economics stating that

‘about 80% of large organizations are at least considering or piloting ITIL, compared to 61% of midsize

organizations and 36% of small organizations’ (2). For ITIL, adoption is clearly on the rise and will be for

the foreseeable future. The Challenge of ITIL adoption has not been so much about understanding its

benefits but more so how to integrate it into the organization and implement the good practices that

enable IT to create more value for the business. This concept is best captured by Thomas Mendel in a

recent Forrester whitepaper ITIL’s Final Breakthrough: From What to How stating ‘Many companies are

talking about it (ITIL), but few have actually fully implemented it’ (3). Depending on the effort scope, ITIL

adoption can be a complex and multi-faceted undertaking with many business and IT considerations to

take into account. Because IT is such a powerful enabler of so many parts of a given organization, ITIL

adoption has the potential to significantly impact the way a business operates and provides service to its

customers. Under normal circumstances, ITIL adoption should result in major organizational changes,

technology investment, and reform in the way peers and leaders communicate and interact. As such,

ITIL adoption should be managed in a way that enables business and IT stakeholders to consider all of

the aspects of adoption so that maximum value can be obtained.

II. Project Management Tools and Practices

Most business and IT managers would agree that Project Management tools and processes provide the

best approach to managing change while maximizing value and return on investment . Project

Management tools and processes also appear to provide the best approach for any organization

endeavoring to adopt ITIL. Frameworks such as the Project Management Body of Knowledge (PMBOK)

appear to be the best suited to support these objectives. In a recent Gartner whitepaper titled ‘How to

Begin ITIL V3 Adoption From Service Strategy the PMBOK Way’ the author states that ‘using PMBOK in

conjunction with ITIL can increase ITIL adoption speed and success, and thus can improve IT operations

process maturity levels faster’ (5). Unfortunately, even with Project Management tools and processes in

place, the vast majority of IT related projects fail for a variety of reasons. A 2007 survey of 800 IT

Managers by Dynamic Markets Limited related to project managements concludes that the mass

majority of projects fail due to ‘overrun on time’, ‘budget overruns’ and ‘higher than expected

maintenance costs’(1). A recent study produced by Keith Ellis of IAG Consulting entitled ‘The Impact of

Business Requirements on the Success of Technology Projects’ also concludes that ‘68% of companies are

more likely to have a marginal project or outright failure than a success’(6). Both assessments conclude

that governance process issues, requirements analysis, communication breakdowns, facilitation, and

stakeholder disagreements are at the core of these project failures. In fact, The IAG study concisely

captures this view stating that ‘Only companies that focus on both the process and the deliverables are

consistently successful at changing project success rates’(6). In this regard, ITIL adoption projects are

akin to standard technology projects and shares the same level of exposure around these core areas.

Most Project Managers are also aware of the enormous risks associated with ignoring these areas of

concern and the negative results that can emerge (e.g. requirements creep, cost overruns, loss of

stakeholder support, etc.). In order to eliminate or mitigate the aforementioned concerns with IT

technology-based projects, many organizations have employed the concept of Project Management

Office (PMO) to help oversee the diverse concerns associated with different project types. Acceptance

of Project Management principles for ITIL adoption efforts has been slow to take hold. The use

of PMOs for ITIL adoption projects has been largely obscure. Nonetheless, the case for managing ITIL

adoption using Project Management and a PMO approach is strong.

III. Project Management Office (PMO) for ITIL Adoption Projects

According to the PMBOK guide- 4th edition, a PMO can be defined as ‘an organizational body or entity

assigned various responsibilities related to the centralized and coordinated management of those

projects under its domain’ (7). A PMO can provide any level of support required to help a project

obtain successful outcomes. In most cases, PMOs are responsible for managing the scope, time, and

cost alignments to the overall quality of a project’s output. Typically, this involves resource

management, compliance concerns, communications, process management, and output integration. If

these areas are not managed closely; each of these areas can significantly impact project outcomes. The

Forrester paper entitled The PMO and Value Realization by Margo Visitacion, summarizes this concept

very well stating that the ‘PMO is in a unique position to deliver on value realization because of its

exposure to both strategic and tactical execution’ (4). The PMO is in the position to positively

impact the outcomes of any project by improving governance and planning, increasing communications

between stakeholders and resources, identifying/facilitating integration needs, monitoring, and

supporting the execution of project processes. ITIL adoption projects greatly benefit from the use of the

PMO structure because it formalizes the relationships between the different aspects of ITIL adoption,

increases collaboration, reduces the risks associated with partial or full project failure, and increases

long term sustainment opportunities.

IV. PMO Models for ITIL Adoption Projects

The PMO Model is a vital component to maximize the chances of success of a target organizations’ ITIL

adoption project. Ensuring that there is an appropriate and effective separation between each

work-stream is paramount to manage the execution and integration of each portion. In addition to

producing the deliverables that correspond to each respective work-stream, each one is responsible for

producing, or contributing to, project oriented artifacts that describe outputs and objectives. Examples

of such artifacts include Project Charter, Project Management Plan, Scope Management Plan,

Work Breakdown Structure (WBS), Quality Management Plan, Risk Register, Communications Plan,

Budget and Cost Estimates. Each Project Manager will need to use their best judgment and work

within the PMO to determine the priority of each deliverable. Depending upon the amount of project

constraints that exist, It may be appropriate to produce these artifacts at the project level instead of the

work-stream level. The objective with producing these artifacts, in addition to providing shape to the

scope, schedule, cost, to the ITIL adoption project, is to define project governance, identify integration

risks and needs, improve communications between stakeholders, and provide business rules for the

execution of project processes. The PMO approach will contribute to the reduction of risk of

undesirable occurrences by clearly defining the interfaces between the different parts and enabling

project leaders and stakeholders to consider the impact to each one when making project decisions.

V. ITIL PMO Model based on Business Concern

The ITIL PMO Model that is based on Business Concerns provides a baseline structure for the Project

Manager and PMO members to manage each business concern in parallel for successful

integration and collaboration. Each business concern is responsible for producing the deliverables

associated with the business concern and working with the Project Managers to manage the interface

between different project parts. The PMO Model is broken into four separate components. They are

defined as follows:

· People: Responsible for managing people requirements and deliverables for an ITIL adoption project. This may include but is not limited to Organizational Change Management, Training, Policies, Standards, Roles, and Responsibilities

· Process: Responsible for managing process requirements and deliverables for an ITIL adoption project. This may include but is not limited to workflow development, procedures, business rules, work instructions, metrics, and key performance indicator development

· Technology: Responsible for managing technology requirements and deliverables for an ITIL adoption project. This may include but is not limited to Systems Architecture, Tools Implementation, Integration Planning, Sustainment Planning , and Report Generation

· Data: Responsible for managing data requirements and deliverables for an ITIL adoption project. This may include but is not limited to Data Attributes, Access Privileges, Information Management, Data Classification, and Data Collection/Automation

clip_image002

Figure 1 - ITIL PMO Model for Business Concerns

The ITIL PMO Model for Business Concerns provides a fantastic model for rapid ITIL adoption and for

supporting related short term objectives. This model allows the PMO to develop project deliverables in

parallel and run multiple activities at one time. This enables the ITIL adoption project to put deliverables

into practice quickly, obtain quick wins with the organization, and produce results swiftly. Depending

upon the level of maturity sought, it can also be the most cost effective PMO model for ITIL adoption

efforts. For optimal use, the PMO model does require the use of an incremental development

approach, which will make it necessary to modify deliverables more than may be what is considered to

be normal practice. Organizations that are more use to a serial project execution approach may

see this as a negative against the use of this model. Project execution models (e.g. Agile) are becoming

more and more popular as approaches for creating deliverables. Organizations that have embraced

Agile or other Iterative development models may be more inclined to embrace this PMO model for ITIL

adoption.

VI. ITIL PMO Model based on Adoption Lifecycle

The ITIL PMO Model that is based on typical Adoption Lifecycle activities also provides a formalized

management structure from which to approach and integrate each lifecycle segment. As part of most

normal ITIL adoption efforts, the activities and outcomes are performed separate but rely upon artifacts

produced from activities for those outcomes. Typically, because of the lack of integration and

collaboration between different ITIL activities, the deliverables produced from these activities don’t

provide as much value as they could. This PMO Structure formalizes the relationships that exist

between each of the activities and their deliverables and increases the opportunities for each

work-stream to team up and work in concert to facilitate successful outcomes. The PMO Model is

broken into four separate components. They are defined as follows:

· Assessment: Responsible for managing Assessment requirements and deliverables for an ITIL adoption project. This may include but is not limited to maturity assessment, senior leadership buy-in, training, requirements gathering, and workshops

· Design: Responsible for managing Design requirements and deliverables for an ITIL adoption project. This may include but is not limited to systems architecture, process design, data architecture, integration planning, roles and responsibilities, and reporting

· Implementation: Responsible for managing implementation requirements and deliverables for an ITIL adoption project. This may include but is not limited to technology implementation, process implementation, data architecture implementation, technology platform migration, and training.

· Sustainment: Responsible for managing Sustainment requirements and deliverables for an ITIL adoption project. This may include but is not limited to continual improvement (e.g. people, process, technology), post implementation workshops, sustainment plans, operational run book development

clip_image004

Figure 2 - ITIL PMO Model for the Adoption Lifecycle

The ITIL PMO Model for the Adoption Lifecycle provides a comprehensive management structure to

execute classic ITIL implementation and support most standard ITIL adoption efforts that use a

sequential approach. The model serves as an empowering force for the multiple workstreams to

collaborate and build upon the efforts of each. By virtue of using such a model, communications

increase between stakeholders and adoption resources, which positively impacts the likelihood of

deriving benefit from artifacts. For optimal use, standard project management practices must be in

place and leveraged with some level of maturity and cross functionally within the target organization.

Compared to the ITIL PMO Model based on Business Concerns, this may be seen as a more top heavy

and cumbersome model than what is required to achieve the business goals. The model would be a

good fit for an organization used to more traditional project management methods and not

comfortable with expeditious change within their organization.

VII. Program Approach

Organizations choosing to adopt more than one process at one time may choose to establish a Program

Management Office instead of a Project Management Office. According to the PMBOK, A Program is

defined as ‘a group of related projects managed in a coordinated way to obtain benefits and control not

available from managing them individually’ (7). Similar to Portfolio Management concepts, the

Program Management approach can coordinate the investment and provide additional influence over

the execution of each project. This gives ITIL adoption efforts greater potential for success in meeting

business strategic goals and requirements through improved communications, collaboration, and

resource synchronization. The Program approach can also enforce standards, policies, and guidelines

across projects through the use of standard templates, models, and other artifacts, which increases the

sustainability of the projects over time. In the model shown below, each project is aligned to a specific

process within the ITIL framework with each project using the ITIL PMO Model for Business Concerns

structure. The ITIL PMO Model for the Adoption Lifecycle could also work within the Program structure.

clip_image006

Figure 3 - ITIL Program Management Model

VIII. Service Management Office

A new and emerging trend to manage ITIL adoption is to establish a semi- permanent organization

known as a Service Management Office (SMO). The SMO is a dedicated resource to manage adoption

concerns and ensure the long term viability of ITIL based solutions. In similar fashion to the Adoption

PMO concept, the SMO seeks to also provide a solid organizational management structure to help

support adoption processes and obtain the greatest value on investment (VOI) from the adoption itself.

The SMO enhances the Adoption PMO approach and structure by also focusing on continual service

improvement (CSI) principles using an expanded Triple Constraint concept. The focus on CSI and

expansion of the Triple Constraint enables the SMO to scrutinize in greater detail additional elements

that contributes directly to the success of an adoption effort and helps create an ITIL based solution that

can provide value and endure for the long term. The SMO Model uses these additional constraints

to help build a structure that can integrate with existing PMO groups to address return on investment

(ROI) concerns as well as provide a comprehensive support resource to facilitate successful project

delivery.  Those additional constraints are defined as follows:

· Integration: Responsible for continual review of new and existing ITIL based solutions for integration into a customer’s environment. The main objective of this constraint is to ensure that the ITIL based solution is interacting with solutions successfully

· Operations: Responsible for managing implementation requirements and deliverables for an ITIL adoption project. This may include but is not limited to technology implementation, process implementation, data architecture implementation, technology platform migration, and training.

· Sustainability: Responsible for managing design requirements and deliverables for an ITIL adoption project. The main objective of this constraint is to ensure that any ITIL based solution is successful in adding value in the production environment

clip_image008

Figure 4 - Example SMO Model

References

1. Computer Economics. (2011 July 7). ITIL Implementation Trending Up but Adoption May Slow. Retrieved from https://www.computereconomics.com/article.cfm?id=1432

2. Dynamic Markets Limited. (2007). IT Projects: Experience Certainty- Independent Market Research Report (1st ed.). Abergavenny, United Kingdom: Dynamic Markets Limited

3. Forrester. (2004). ITIL’s Final Breakthrough: From What to How (1st ed). Cambridge, MA: Thomas Mendel, PHD

4. Forrester. (2004). The PMO and Value Realization (1st ed.). Cambridge, MA: Margo Vistacion.

5. Gartner. (2011). How to begin ITIL v3 Adoption from Service Strategy the PMBOK Way (1st ed.). Stanford, CT: Tapati Bandopadhyay, Patricia Adams

6. IAG Consulting. (2008). Business Analysis Benchmark – The Impact and Business Requirements on the Success of Technology Projects (1st ed.). Toronto, Canada : Keith Ellis

7. Pennypacker, James S. (eds.). (2008). A Guide to the Project Management Body of Knowledge (4th Ed). Newton Square, PA, Project Management Institute Publications

Comments

  • Anonymous
    January 01, 2003
    Congratulations.

  • Anonymous
    January 01, 2003
    Very interesting - I work in adoption a lot and this is one angle i hadn't considered.

  • Anonymous
    April 17, 2013
    Fantastic integration of PMO and SMO. Hopefully PMBOK will include an area for service delivery and infrastructure management in the future.

  • Anonymous
    September 30, 2015
    Its really helpful for me to manage a software project through it looking forward for future post tanks for sharing #http://www.trainingintambaram.in/android-training-in-chennai.html# & #http://www.trainingintambaram.in/software-testing-training-in-chennai.html

  • Anonymous
    October 01, 2015
    Hi, It really understand that the lot of new information.


    http://www.besanttechnologies.com/training-courses/web-designing-training/node-js-training-in-chennai


  • Anonymous
    November 23, 2015
    Hi, and welcome to PMO Planet (Portfolio Management Office or Programme .... This got me into thinking… do the best Project Managers (PM's) apply ..... of bringing in new PPM / PMO practices from consultants and training, and ... PMO Planet's Top 20 Mandela quotes for PMO's and Project Professionals. http://goo.gl/LYLHhG

  • Anonymous
    November 26, 2015
    Nice article. Nice article. Certificate IV of Project Management or Diploma in Project Management, reflects the cross-industry application of the work functions normally undertaken by a project team, spanning all phases of a project from concept through to close-out. You will gain valuable skills, including setting timelines and targets, project costing, budget management, quality control, communicating with key stakeholders as well as recruiting and leading personnel to work on the project. http://avli.com.au/courses/certificate-iv-project-management-practice

  • Anonymous
    November 27, 2015
    Many organizations profit hugely by utilizing a Project Management Office (PMO), it means they achieve benefits from standardizing and following project management policies, processes, and methods. However, building an effective PMO is a complex process; it requires clear vision and strong leadership so that, over time, it will become the source for guidance, documentation, and metrics related to the practices involved in managing and implementing projects.http://goo.gl/Ksdrqj